Question: You are overseeing a construction project that includes the following phases: Site Preparation ( 3 weeks ) Foundation Work ( 4 weeks ) Framing (

You are overseeing a construction project that includes the following phases:
Site Preparation (3 weeks)
Foundation Work (4 weeks)
Framing (5 weeks)
Roofing (2 weeks)
Interior Work (3 weeks)
Final Inspection (1 week)
Draw a Gantt chart to illustrate the timeline for the construction project. Assume the project starts on July 1 and highlight any dependent tasks that cannot start until the previous task is completed.