Question: You are planning the resourcing for a project and create a visual representation that illustrates the number of hours that each person will be needed

You are planning the resourcing for a project and create a visual representation that illustrates the number of hours that each person will be needed each week over the course of the project schedule. This visual representation is commonly known as a:

A. Work breakdown structure

B. Task network diagram

C. Resource histogram

D. Detailed Gantt chart