Question: You are planning the resourcing for a project and create a visual representation that illustrates the number of hours that each person will be needed
You are planning the resourcing for a project and create a visual representation that illustrates the number of hours that each person will be needed each week over the course of the project schedule. This visual representation is commonly known as a:
| A. Work breakdown structure | ||
| B. Task network diagram | ||
| C. Resource histogram | ||
| D. Detailed Gantt chart |