Question: You are planning the schedule for your application development project. For a specific program P to be developed, you assigned the task of coding to
You are planning the schedule for your application development project. For a specific program P to be developed, you assigned the task of coding to John and the task of code review to Kelly. Both John and Kelly should work together to code the program and review the code respectively and both the activities should be finished simultaneously. You defined two activities PCode and PReview for coding and code review activities respectively. What should be the dependency between these two activities?
Question options:
A
Finish to Finish
B
Start to Finish
C
Finish to Start
D
Start to Start