Question: You are planning to launch a project to purchase, install and integrate new technology for your entire office of 3 0 employees. You considered a
You are planning to launch a project to purchase, install and integrate new technology for your entire office of employees. You considered a similar project you heard of that cost $ per unit and you know you have units to replace. Which type of cost budgeting have you used?
Bottomup
Proforma
Analogous
Parametric