Question: You are planning to launch a project to purchase, install and integrate new technology for your entire office of 3 0 employees. You considered a

You are planning to launch a project to purchase, install and integrate new technology for your entire office of 30 employees. You considered a similar project you heard of that cost $100,000 per unit and you know you have 20 units to replace. Which type of cost budgeting have you used?
Bottom-up
Proforma
Analogous
Parametric