Question: You are preparing an estimate and need to develop hourly cost for the following crafts: Laborer Carpenters Finishers Base Rate $15.00 $20.00 $18.00 Fringe Benefits

You are preparing an estimate and need to develop hourly cost for the following crafts: Laborer Carpenters Finishers Base Rate $15.00 $20.00 $18.00 Fringe Benefits as % of Payroll: Pension 7.5% 7.5% 7.5% Welfare 3.5% 3.5% 3.5% Health 4.0% 4.0% 4.0% Insurance 20.0% 20.0% 13.0% Payroll Taxes 20.0% 20.0% 20.0% What is the hourly cost of a laborer? $18.84 $15.94 $23.25 O $25.44
Step by Step Solution
There are 3 Steps involved in it