Question: You are required to: a) Complete the MRP sheet using Lot-for-Lot technique b) Calculate total cost of Lot-For-Lot Technique c) Calculate the value of EOQ

You are required to:

a) Complete the MRP sheet using Lot-for-Lot technique

b) Calculate total cost of Lot-For-Lot Technique

c) Calculate the value of EOQ using the information given in the MRP sheet

d) Calculate total cost including Setup cost and holding cost of EOQ

e) Find the value of Order Size (New EOQ) using your SAP ID (for SAP ID 70077555, sum all values 7+0+0+7+7+5+5+5=36) Order Size (New EOQ) would be 36

f) Calculate total cost including Setup cost and holding cost of Order Size (New EOQ).

g) Compare the total cost of part b, d and f and select the optimal option

Weeks

1

2

3

4

5

6

7

8

Gross requirements

47

21

63

11

41

21

43

39

Scheduled receipts

10

20

20

Projected on hand

37

Net requirements

Planned order receipts

Planned order releases

Additional Information:

Setup cost $200,

Holding cost $3 per unit/per week,

Lead time 2 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!