Question: You are responsible for a project with high risks, particularly during the early phases. Your sponsor has asked for performance reports on a monthly basis.

You are responsible for a project with high risks, particularly during the early phases. Your sponsor has asked for performance reports on a monthly basis. At the end of the first month, you report a CPI and SPI greater than 1. What would this mean?