You are tasked with constructing a cash flow projection for a contractor's project for a 100,000-square-foot...
Fantastic news! We've Found the answer you've been seeking!
Question:
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/6646822ba8aee_8756646822b89d28.jpg)
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/05/6646822c20f9a_8766646822c02a33.jpg)
Transcribed Image Text:
You are tasked with constructing a cash flow projection for a contractor's project for a 100,000-square-foot parking lot project. The holdback retention rate is 10%. Given the provided data, what's the anticipated net cash flow for Month 2? Assume a one- month payment lag and no holdback releases or interest. Contractor's Planned Schedule Construction Work Planned Schedule of Month Package Duration Values Earthwork 2.00 $500,000 1 $250,000 2 3 4 5 Gravel Base 2.00 $1,000,000 $250,000 $500,000 Pavement 2.00 $1,500,000 Total direct & indirect costs $3,000,000 Overhead 10% Profit 5% Total for contract $250,000 $750,000 $300,000 $25,000 $75,000 $150,000 $12,500 $37,500 $3,450,000 $287,500 $862,500 $500,000 $750,000 $750,000 $1,250,000 $750,000 $125,000 $75,000 $62,500 $1,437,500 $862,500 $37,500 ($428,750) ($703,750) $905,625 ($566,250) You are preparing an equipment cost control report using the following progress data. What would be the Total Equipment Variance for the project? Equipment Cost Control Report Job Code Job Description Budgeted Equipment Machine Hours Budgeted Unit Price per Machine Hour Actual Machine Hours Actual Unit Price per Machine Hour Installation of 08.100.03 Mobile Crane 250 $250 250 $265 Curtain Walls Installation of 08.200.03 Mobile Crane 50 $100 40 $150 Exterior Doors Total 300 290 $5,250 Under Budget $4,750 Under Budget $11,500 Under Budget $4,750 Over Budget You are tasked with constructing a cash flow projection for a contractor's project for a 100,000-square-foot parking lot project. The holdback retention rate is 10%. Given the provided data, what's the anticipated net cash flow for Month 2? Assume a one- month payment lag and no holdback releases or interest. Contractor's Planned Schedule Construction Work Planned Schedule of Month Package Duration Values Earthwork 2.00 $500,000 1 $250,000 2 3 4 5 Gravel Base 2.00 $1,000,000 $250,000 $500,000 Pavement 2.00 $1,500,000 Total direct & indirect costs $3,000,000 Overhead 10% Profit 5% Total for contract $250,000 $750,000 $300,000 $25,000 $75,000 $150,000 $12,500 $37,500 $3,450,000 $287,500 $862,500 $500,000 $750,000 $750,000 $1,250,000 $750,000 $125,000 $75,000 $62,500 $1,437,500 $862,500 $37,500 ($428,750) ($703,750) $905,625 ($566,250) You are preparing an equipment cost control report using the following progress data. What would be the Total Equipment Variance for the project? Equipment Cost Control Report Job Code Job Description Budgeted Equipment Machine Hours Budgeted Unit Price per Machine Hour Actual Machine Hours Actual Unit Price per Machine Hour Installation of 08.100.03 Mobile Crane 250 $250 250 $265 Curtain Walls Installation of 08.200.03 Mobile Crane 50 $100 40 $150 Exterior Doors Total 300 290 $5,250 Under Budget $4,750 Under Budget $11,500 Under Budget $4,750 Over Budget
Expert Answer:
Posted Date:
Students also viewed these finance questions
-
Determine the real roots of (x) = - 1 + 5.5x 4x2 + 0.5x3: (a) Graphically and (b) Using the Newton-Raphson method to within s = 0.01%.
-
Burkhart Enterprises wants you to prepare a spreadsheet to answer the following questions: A. Purchases (net of discount) of inventory were $ 500,000 during the period. The beginning balance of...
-
Make a list of three products or services to which you are brand-loyal For each, explain why you have highly favorable attitudes toward the brand and consciously seek to buy it whenever you make a...
-
What are some potential roles for advisory councils? How can organizations use these groups effectively?
-
Bennett Construction Company is a building contractor specializing in small commercial buildings. The company has the opportunity to accept one of two jobs; it cannot accept both because they must be...
-
A company is considering investing in a project that is expected to yield the following from the project is 12%. Initial Outflow $185,000 Cash Flow Year 1 = $105,000 Cash Flow Year 4 = $180,000 Cash...
-
generate an sql query for this question- What is the average duration of the most popular videos? a. This question involves understanding video duration trends, which can be essential for content...
-
What methods can be used to identify communications?
-
What topics would be addressed within the project Communications Management Plan?
-
How can organisational change management assist the project manager?
-
What is VARK? Why is it important?
-
What are non-verbal cues, and why are they important to a project manager?
-
The record of employment is filed with: Multiple Choice Canada Pension Plan Revenue Quebec The Canada Revenue Agency Service Canada The Employment Insurance Board
-
Extend Algorithms 3.4 and 3.5 to include as output the first and second derivatives of the spline at the nodes.
-
Which theory emphasizes the importance of cooperation and participation in the workplace? A. Chaos Theory. B. Systems Theory. C. Classical Theory. D. Neoclassical Theory.
-
Line and staff positions are identified on the organization chart. What does the line position denote? A. Who is responsible to whom within the organization. B. Advisory relationships between...
-
Which one of the following sets the standards for behavior within the organization? A. The mission. B. The values. C. The philosophy. D. The vision.
![Mobile App Logo](https://dsd5zvtm8ll6.cloudfront.net/includes/images/mobile/finalLogo.png)
Study smarter with the SolutionInn App