Question: You are tasked with evaluating three possible foundation design alternatives for a new bridge considering extreme flood limit state, possible damage, and repair cost, and
You are tasked with evaluating three possible foundation design alternatives for a new bridge considering extreme flood limit state, possible damage, and repair cost, and a year design service life. The occurrence of an Extreme Flood Event is best estimated by the Poisson distribution and the AASHTO standards require that foundations are designed for an extreme flood event with a year recurrence Hint: annual occurrence is year Associated costs and conditional probabilities are listed in the following table.
Find: Using DecisionTree Analysis Method provide the following:
a Construct the decision tree model representing each alternative decision and all possible outcomes
b Determine expected value cost for each foundation type and the preferred decision based on the minimum expected cost criteria.
c Determine the expected value of perfect information EVPI
d Develop a cumulative risk profile for each foundation decision.
e Which strategy is preferred based on total risk? Explain
f Assume that a flood study can be performed at the proposed bridge location. The firm you plan to hire has conducted several flood studies in that region, and of those studies resulted in reports that forecasted significant flood events. Further, the actual occurrence of significant flood events in the region was accurate compared to the firms reports. What is the expected value of this firms flood study EVSI Should you hire them? Explain?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer