Question: You are tasked with managing a project that has the following activities (time is given in weeks) and precedence relationships: a. Calculate the expected completion

You are tasked with managing a project that has the following activities (time is given in weeks) and precedence relationships:

You are tasked with managing a project that has

a. Calculate the expected completion times for each of the project activities.

b. Calculate the variance of the completion times for each of the project activities.

c. Sketch the project activity network.

d. Determine the project critical path.

e. What is the expected project completion time?

f. The project needs to be completed 12 weeks from now. What is the probability this deadline will be met?

Activity A B D E Optimistic Most Likely Pessimistic Immediate Time Time Time Predecessors 4 7 2 2 8 3 3 9 B 2 2 2 C,D 1 1 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!