Question: You are the project manager for a construction project. The total cost of the project is $12 million. At this point in the project, your
You are the project manager for a construction project. The total cost of the project is $12 million. At this point in the project, your plan assumed construction would be 65% complete. You calculate the SPI and it is currently 0.97. What do you report to your sponsor about the project's performance? Construction is on schedule. Nothing yet - more variables are needed Construction is behind schedule. Construction is ahead of schedule