Question: You are the project manager for a Greg Builder Homes construction project. Based on customer feedback, you need to reduce the duration of the project.
You are the project manager for a Greg Builder Homes construction project. Based on customer
feedback, you need to reduce the duration of the project. Hereunder is a table showing all
relevant project information necessary to look at options to crash the project. You also have
calculated the normal indirect costs of the project to be $k which could be reduced by $k
for each month reduction in project duration.
Based on the Chart, Crash the project schedule showing the direct, indirect and total costs for each crashing
step between normal duration and minimum duration after maximum crashing. For
each of the crashing steps, document what activityies isare crashed, and what are the
related direct, indirect and total costs for the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock