Question: You are the project manager for a new project and have figured out the following: dependencies: Activity 1 can start immediately and has an estimated
- You are the project manager for a new project and have figured out the following: dependencies:
- Activity 1 can start immediately and has an estimated duration of 3 weeks
- Activity 2 can start after activity 1 is completed and has an estimated duration of 3 weeks
- Activity 3 can start after activity 1 is completed and has an estimated duration of 8 weeks
- Activity 4 can start after activity 2 is completed and has an estimated duration of 8 weeks
- Activity 5 can start after activity 4 is completed and after activity 3 is completed. This activity takes 5 weeks. Draw a network diagram
- What is the duration of a milestone?
- It is shorter than the duration of the longest activity.
- It is shorter than the activity it represents.
- It has no duration.
- It is the same length as the activity it represents.
Type or paste question here
Step by Step Solution
There are 3 Steps involved in it