Question: You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations
You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations (releases). Each of the iterations will take 20 days to complete, at a cost of $20,000 per iteration. Today is the end of what should be iteration three.
The current status of the project is as follows:
Iteration One complete, spent $20,000
Iteration Two complete, spent $25,000
Iteration Three half done, spent $17,000
Iteration Four Not started.
Please provide the following values: PV, EV, AC, CPI, SPI, EAC, ETC, BAC