Question: You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations

You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations (releases). Each of the iterations will take 20 days to complete, at a cost of $20,000 per iteration. Today is the end of what should be iteration three.

The current status of the project is as follows:

Iteration One complete, spent $20,000

Iteration Two complete, spent $25,000

Iteration Three half done, spent $17,000

Iteration Four Not started.

Please provide the following values: PV, EV, AC, CPI, SPI, EAC, ETC, BAC

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!