Question: You are the project manager for a project to set up a new web server and decommission the old server. You are responsible for selecting
You are the project manager for a project to set up a new web server and decommission the old server. You are responsible for selecting the appropriate personnel for the project team. Which of the following would not be a responsibility for these team members? Estimating task duration, estimating task costs, creating the project schedule, or contributing expertise to the project