Question: You are the project manager for a project within your company. The project work is scheduled to last six months. To meet this deadline, you
You are the project manager for a project within your company. The project work is scheduled to last six months. To meet this deadline, you had to schedule overtime for the project team each week. Human resources agreed with the project team that this was an excessive request. You have since applied resource leveling to the project. What is the likely result of this action?
A The project team will not have to work overtime all of the weeks, but only some of the weeks.
B The project team will not have to work overtime at all through the project, but will have to work on work packages they are not competent in
C The project team will need additional team members because of the additional work.
D The project team will need additional team members in order to meet the project deadline.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock