Question: You are the project manager for a two - year project that is now beginning its second year. The mix of team members has changed,

You are the project manager for a two-year project that is now beginning its second year. The mix of team members has changed, and there is confusion as to roles and responsibilities. In addition, several of the completed work packages have not received the required sign-offs, and three work packages are five weeks behind schedule. To gain control of this project, you need to
Select one:
A. Rebaseline your original human resource plan with current resource requirements
B. Change to a projectized organizational structure for maximum control over resource assignments
C. Work with your team to prepare a responsibility assignment matrix
D. Create a new division of labor by assigning technical leads to the most critical activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!