Question: You are the project manager for the KOY Project, which requires quality that maps to federal guidelines. During a quality audit, you discover that a
You are the project manager for the KOY Project, which requires quality that maps to federal guidelines. During a quality audit, you discover that a portion of the project work is faulty and must be redone. The requirement to redo the work is an example of which of the following? Group of answer choices Cost of nonconformance Cost of quality Cost of adherence The cost of doing business