Question: You are the project manager for the project to replace eLearn at Stonehill. You have been able to shorten an activity from 8 days to

You are the project manager for the project to replace eLearn at Stonehill. You have been able to shorten an activity from 8 days to 5 days. This activity is NOT on the critical path. This reduction will impact the project schedule how: