Question: You are the project manager for the Sweep Time software project. You have decided to use the beta distribution, or 3-point estimation, technique for this
You are the project manager for the Sweep Time software project. You have decided to use the beta distribution, or 3-point estimation, technique for this project. For the "phase 1 test" activity in days, the following estimates are available: O=5, P=10, M=6.
What is the result of this estimate in the example?