Question: You are the Project Manager involved in a complex refurbishment of an historic building. This has been procured under Option A of the ECC. Secondary
You are theProject Managerinvolved in a complex refurbishment of an historic building. This has been procured under Option A of the ECC. Secondary Option X delay damages is included. A first programme was identified in Contract Data. The project includes extensive work by other specialist contractors employed by theClient
a
Describe how the contract recognises such specialists that are directly engaged by theClient What obligations are placed on theContractorto liaise and incorporate the specialists work into their own plans?
TheContractorshows on the Accepted Programme that one of these specialists is required to provide concrete plinth details by week of the contract, which they fail to do This directly impacts upon theContractorsability to meet a Condition stated for a Key Date.
b
What should theContractordo as soon as becoming aware of this? Is there a time limit for this? marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock