Question: You are the project manager of a systems implementation project. Your team has started testing a deliverable with the customer observing the process. The testing
You are the project manager of a systems implementation project. Your team has started testing a deliverable with the customer observing the process.
The testing has uncovered many defects that are all being duly noted and submitted back to the appropriate technical team members to fix. Some of these
fixes have an impact on the project, so you are performing an impact analysis and submitting the request to the CCB Which of the following statements is
correct?
A The PM is performing change control, the team is performing quality assurance, and the customer is performing quality control.
B ThePMis controlling the scope, the team is performing quality control, and the customer is performing validate scope.
C ThePMis performing quality control, the team is performing validate scope, and the customer is observing.
D The PMis performing validate scope, the team is performing quality control, and the customer is performing quality assurance.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock