Question: You are the project manager on a $1,000,000 housing development project that has an estimated duration of five month. You are at the end of

You are the project manager on a $1,000,000 housing development project that has an estimated duration of five month.

You are at the end of month two. According to the project estimate, your team should be done with 40% of the work.

As of today, the project is 45% complete while 50% budget has been used. Show your conclusion about the project performance below. Choose the right options from the drop-down list.

BAC = blank

AC = blank

PV = blank

EV = blank

CPI = blank

SPI = blank

Since CPI is blank, the project is blank budget.

And since SPI is blank , the project is blank of schedule.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!