Question: You are the project manager responsible for customizing and installing your company's software at the client site. You've completed the Initiation process and are now

You are the project manager responsible for customizing and installing your company's software at the client site. You've completed the Initiation process and are now working on the Planning processes. This project has a completion date of December 1. You've penciled in Kathy as the lead programmer for this project. She is tentatively scheduled to work on this project starting July 1 and ending November 4. She and her manager have always agreed to work on your projects in the past. This is an example of: C vet availability