Question: You are the project manager working for Mack's Pool Co . Your project consists of installing a new hot tub at a client's patio. You

You are the project manager working for Mack's Pool Co. Your project consists of installing a new hot tub at a client's patio. You would like to find the minimum cost schedule for your project. There is a $50 per week penalty for each week the project is delayed beyond week 13. In addition, your project team determined that indirect costs are $15 per week.
\table[[ACTIVITY,\table[[Immediate],[Predecessor],[(s)]],\table[[NORMAL],[TIME (NT)]],\table[[CRASH],[TIME (CT)]],\table[[Normal],[Cost (NC)]],\table[[Crash],[Cost],[(CC)]]],[A,--,2,1,50,70],[B,A,4,2,80,160],[C,A,8,4,70,110],[D,A,6,5,60,80],[E,B,7,6,100,130],[F,D,4,3,40,100],[G,C, E, F,5,4,100,150]]
Before crashing, the project duration is week(s).
 You are the project manager working for Mack's Pool Co. Your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!