Question: You are the shift supervisor that assembles laptop computers in a new facility and need to develop an improved layout design. What would be the

You are the shift supervisor that assembles laptop computers in a new facility and need to develop an improved layout design. What would be the minimum number of workstations if the total task time is 48 minutes per laptop and the cycle time is 11 minutes per laptop? A)4 workstations B)6 workstations C)4.4 workstations D)5 workstations