Question: You are the supervisor at a manufacturing facility for one specific component in a much larger piece of machinery. You have been given the
You are the supervisor at a manufacturing facility for one specific component in a much larger piece of machinery. You have been given the following Master Production Schedule and figuring out how many components you have Available-to- Promise. Complete the table and show your work (10 Marks) (Answer: ATP1=, ATP2= etc) MODEL C MPS (BI= 250) CCO ATP: D 500 650 2 200 100 3 200 100 4 0 200 5 200 50 6 200 0 7 0 8 200 100 You are the supervisor at a manufacturing facility for one specific component in a much larger piece of machinery. You have been given the following Master Production Schedule and figuring out how many components you have Available-to- Promise. Complete the table and show your work (10 Marks) (Answer: ATP1=, ATP2= etc) MODEL C MPS (BI= 250) CCO ATP: D 500 650 2 200 100 3 200 100 4 0 200 5 200 50 6 200 0 7 0 8 200 100
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
To calculate the AvailabletoPromise ATP for each period we need to work through the Master Productio... View full answer
Get step-by-step solutions from verified subject matter experts