Question: You are to create a weighted average selection table in Excel in order to select the best proposal based upon this weighted average approach. Please

You are to create a weighted average selection table in Excel in order to select the best proposal based upon this weighted average approach. Please highlight the column with the best proposal in yellow. Please paste a screenshot of the Excel table of the weighted average approach in a Word document and write a paragraph (four to seven sentences) in the same Word document as to why this vendor would be the best choice. The information about the vender choices are as follows:
You have received three possible solutions from three different vendors. This project has two constraintscost and schedule. Management has determined that a cost of $15,000 or less would be good but up to $20,000 is acceptable. Management also has determined that a completion time of 180 days or less would be good but up to 240 days would be acceptable. The business user team has determined that there are five business requirements that they would like to see with the final product.
The firm utilizes a numbering system between 1 and 5 to determine if the vendors proposal satisfies the constraints and requirements. For constraints, the firm usually rates proposals that meet the good criteria with the number 5, proposals that meet acceptable with the number 3, and those that do not meet the criteria limits would be rated with the number of 1. Regarding requirements, if the proposal fully satisfies the requirement, then it would be rated with the number 5. If the proposal satisfies at least 60% of the requirement, then it would be rated with the number 3. All other proposals that do not satisfy at least 60% of the requirement would be rated with the number 1.
Furthermore, the importance of the constraints and requirements based on a 100% scale are as follows.
Cost Constraint is 20%.Schedule is 10%.Requirement 1 is 20%.Requirements 2 and 3 are 15% each.Requirements 4 and 5 are 10% each.
Your job as a systems analyst is to review the proposals below and determine which vendors proposals will be awarded the contract for the project based on a weighted average approach.
Project Proposals
Vendor A
Vendor B
Vendor C
Constraint Cost
$20,750.00
$19,500.00
$14,950.00
Schedule
160 days
200 days
250 days
Requirement 1
Fully Meets
Fully Meets
75% Meets
Requirement 2
75% Meets
50% Meets
Fully Meets
Requirement 3
Fully Meets
Fully Meets
Fully Meets
Requirement 4
Fully Meets
Fully Meets
50% Meets
Requirement 5
75% Meets
75% Meets
75% Meets

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!