Question: You are using earned value analysis for your project. You have posted the data to your team: PV = $ 2 2 0 0 EV

You are using earned value analysis for your project. You have posted the data to your team:
PV = $2200
EV = $2000
AC = $2500
BAC = $10,000
What is the cpi of this project and what does it tell us about cost performance?
a.0.20- cost is to plan
b.0.80- actual costs have exceeded planned costs
c.0.80- actual costs are less than planned costs
d.1.25- actual costs are aboveplannedcosts