Question: You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.
A) Your CEV is RM3.8million, while your CAC is RM4.6 million, calculate your CPI and explain what does it indicate.
B) Based on the above data, what is your CV?
C) Calculate your FCAC using both methods. Your total budget is RM 5.7 million Explain the difference?
D) Calculate TCPI, and explain what it means.