Question: You are using the earned value technique for project performance reporting for an existing project. You disseminated a report to all key stakeholders displaying the

You are using the earned value technique for project performance reporting for an existing project. You disseminated a report to all key stakeholders displaying the following cost information listed below. Using the principle of Earned Value Management, what can be said about the project? PV= $ 4,000 , EV= $ 3,200 , AC= $ 4,500 , BAC= $ 10,000