You are working as a site engineer at a site of a multistory commercial building with raft
Fantastic news! We've Found the answer you've been seeking!
Question:
You are working as a site engineer at a site of a multistory commercial building with raft foundation. Prepare and Label a bar chart showing the super structure’s work from DPC to the de shuttering of ground floor’s slab form work. Divide the work into small activities with their durations. There will be no work on 4th and 9th day from the starting day. Accommodate these off-working days in the bar chart. Draw the chart with
proper scale or on graph paper.