Question: You are working on a project to set up a call center for your client. The duration of the project is two years. One year

You are working on a project to set up a call center for your client. The duration of the project is two years. One year has passed, however, only 40% of the work has been completed against the schedule, which says that by now 60% of the work should have been completed. To date, you have spent 50% of the budget. What is the cost performance index of the project at this one year milestone?
Question 4 options:
1.25
0.8
0.67
1.5