Question: You are working to establish a technical priority in matrix 6 of the HOQ. There are 3 customer needs. Need 1 has and overall weighting

You are working to establish a technical priority in matrix 6 of the HOQ. There are 3 customer needs. Need 1 has and overall weighting of 41.9 need 2 has 23.5 and need 3 has 11.5. The technical requirement under consideration has an interrelationship value with need 1 of 1, need 2 of 2 and need 3 of 4. What is the technical priority of the requirement?

Please solve it with clear handwriting with all steps (think you are giving a solution to the kid

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock