Question: You are working to reduce the work in process inventory for a spoon production work cell. The cell produces three types of spoons: the Sicily
You are working to reduce the work in process inventory for a spoon production work cell. The cell produces three types of spoons: the Sicily Serving Spoon, Malta Tablespoon, and Sardinia Teaspoon. Calculate the required number of kanbans for each of the products. Assume that the work cell operates 5 days/week with one 8-hour shift per day. During their 8-hour shift, workers have a 30-minute paid lunch break and two breaks of 15 minutes each. Data is shown in the table.
| Sicily | Malta | Sardina | |
| Customer Demand | 120 per day | 80 per week | 45 per hour |
| Conveyance Time | 5 hours | 1 day | 5 minuted |
| Container capacity | 25 units | 15 units | 5 units |
| Safety Margin | 10% | 0% | 15% |