you can only take one of the following two projects. You have no capital constraints and the
Fantastic news! We've Found the answer you've been seeking!
Question:
you can only take one of the following two projects. You have no capital constraints and the cost of capital is 10%. The information below for each project includes the IRR and NPV.
Project A: Costs 500 dollars today, pays 200 at t = 1 year from now, pays 250 at t = 2 years from today, and pays 300 at t = 3 years from today. The IRR is 21.65%. The NPV is $113.82.
Project B: Costs 750 dollars today, pays 300 at t = 1 year from now, pays 350 at t = 2 years from today, and pays 400 at t = 3 years from today. The IRR is 17.93%. The NPV is $112.51.
Required
calculate which project should be the best choice?
Related Book For
Cornerstones of Managerial Accounting
ISBN: 978-0324660135
3rd Edition
Authors: Mowen, Hansen, Heitger
Posted Date: