Question: You completed mapping the current state. Your customers take 15 days to receive the delivery of the product from the time of its order. It

You completed mapping the current state. Your
You completed mapping the current state. Your customers take 15 days to receive the delivery of the product from the time of its order. It takes 3 hours to produce one unit of the product to meet the customer requirements. The approximate amount of time required to handle a process in the production step is 1.5 hours. Wha is the Lead Time of this process

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer