Question: You created the network diagram for your project based on the chart when all of a sudden, the person completing activity C says you must
You created the network diagram for your project based on the chart when all of a sudden, the person completing activity C says you must plan for a lag of two weeks after the completion of the activity before starting the next activity. Which of the following is the first thing to do?
| a. | See if the duration of activity H can be shortened. | |
| b. | Nothing, because the two weeks could be assigned to activity E. | |
| c. | Calculate project float after the insertion of the lag. | |
| d. | Make Start, A, D, G, End the critical path in order to save time. |