Question: You have a manager who informs you that the year long project ( linear spend plan ) they are executing currently ( Imagine today is
You have a manager who informs you that the year long project linear spend plan they are executing currently Imagine today is January st has spent half their budget of $ and they show a CPI of and an SPI of On what date will this project finish and what is your EAC?