Question: You have a project that must be completed in 1 2 months and the budget is 1 0 0 , 0 0 0 USD. Six

You have a project that must be completed in 12 months and the budget is 100,000 USD. Six months have passed, and the schedule says that 50% of the work should be completed. What is the projects Planned Value
(P V)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock