Question: You have a project that must be completed within 1 2 months at a cost of R 1 0 0 , 0 0 0 .

You have a project that must be completed within 12 months at a cost of R100,000. Six months have passed and R50,000 should have been spent, but after an in-depth review of the project, you discover that only 40% of the work has been completed so far. What is the schedule performance index (SPI) for this project?
Question 12Select one:
a.
0.9
b.
0.4
c.
0.3
d.
0.8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock