Question: You have a project to be completed in 1 2 months. The budget is 1 0 0 , 0 0 0 USD. Six months have
You have a project to be completed in months. The budget is USD. Six months have passed, and USD has been spent already, but upon closer review, you find that only of the work has been completed so far. What is the projects Actual Cost AC
$
$
$
$