Question: You have a project to be completed in 1 2 months. The budget is 1 0 0 , 0 0 0 USD. Six months have

You have a project to be completed in 12 months. The budget is 100,000 USD. Six months have passed, and 80,000 USD has been spent already, but upon closer review, you find that only 40% of the work has been completed so far. What is the projects Actual Cost (AC)?
$60,000
$100,000
$80,000
$40,000