Question: You have been analyzing one value stream and have discovered the following: Category Minutes average cycle time 7 5 0 business value add 7 5

You have been analyzing one value stream and have discovered the following:
Category Minutes
average cycle time 750
business value add 75
documentation 20
inspection 30
lunch 30
non-value add 600
value add 75
What is the value add ratio?