Question: You have been assigned a project that is halfway through its execution. You have had to take up this project due to non - availability
You have been assigned a project that is halfway through its execution. You have had to take up this project due to nonavailability of the current project manager. This is a complex project involving multiple contractors and teams at various geographical locations. You decide to look up the requirements of the types of reports and frequency of sending them. Where would you find this information?
SELECT THE CORRECT ANSWER
Project Management Plan
Scope Management Plan
Communication Management Plan
Stakeholder Analysis