Question: You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A cash flow Project B
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows:
| Year | Project A cash flow | Project B cash flow |
|
| 0 | $(110,000) | $(110,000) | |
| 1 | 30,000 | 00 | |
| 2
| 30,000 | 00 | |
| 3 | 30,000 | 00 | |
| 4 | 30,000 | 00 | |
| 5 | 30,000 | 230,000 |
If the appropriate discount rate on these projects is
8%,
which would be chosen and why?