Question: You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Cash Flow Project B
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows:
Year Project A Cash Flow Project B Cash Flow 0 $(102,000) $(102,000) 1 $30,000 $0 2 $30,000 $0 3 $30,000 $0 4 $30,000 $0 5 $30,000 $215,000
If the appropriate discount rate on these projects is11 percent, which would be chosen and why?
The NPV of Project A is what?