Question: You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flow: Year Project a Cash Flow Project B
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flow:
Year Project a Cash Flow Project B Cash Flow
0 $-105,000 $-105,000
1 30,000 0
2 30,000 0
3 30,000 0
4 30,000 0
5 30,000 200,000
If the appropriate discount rate on these projects is 9 percent, which would be chosen and why
What is the NPV of project a?
$____ (Round to the nearest cent)
What is the NPV of project B?
$____ (Round to the nearest cent)
Which project would be chosen and why
A) choose both because they have a positive NPV's
B) Choose B because its NPV is higher
C) Choose A because its NPV is higher
D) Cannot choose without comparing the IRRS
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
