Question: You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Cash Flow Project B
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows:
| Year | Project A Cash Flow | Project B Cash Flow |
|---|---|---|
| 0 | $(95,000) | $(95,000) |
| 1 | 40,000 | 0 |
| 2 | 40,000 | 0 |
| 3 | 40,000 | 0 |
| 4 | 40,000 | 0 |
| 5 | 40,000 | 210,000 |
If the appropriate discount rate on these projects is 11 percent, which would be chosen and why?