Question: You have been called in as a consultant to set up a Kanban control system. The first thing to do is to determine the number
You have been called in as a consultant to set up a Kanban control system. The first thing to do is to determine the number of Kanban card sets needed. Your research shows that the expected demand during lead time for a particular component is 150 per hour. You estimate the safety stock should be set at 25 percent of the demand during lead time. The tote trays used as containers can hold 8 units of stock, and the lead time it takes to replenish an order is 2 hours. You found that the number of Kanban cards needed is 47. Your client now tells you that they miscalculated the demand and the true demand is 300 per hour. All other things remain the same. What is the most appropriate answer from the choices below?
Multiple Choice
-
Number of Kanban cards will decrease to 24.
-
Number of Kanban cards will stay the same at 47.
-
Number of Kanban cards will increase to 107.
-
Number of Kanban cards will increase to 113.
-
Number of Kanban cards will increase to 94.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts