Question: You have been given information in the table below relating to one of the projects involving the installation of control devices. You are expected to
You have been given information in the table below relating to one of the projects involving the installation of control devices. You are expected to determine the following, Completion time of the project and the activities that are on the critical path. Probability of completing this project in 53 days The days that allow for 99% probability completion for the project. Relevant illustrations should be provided in your response. (Round off to 2 decimal places)

Activity A B C D E F LL G H J K L M N Immediate Predecessor A A B,C D D E,F G,H I 1 J K L,M Optimistic Time 4 1 6 5 1 2 1 4 2 2 1 6 Most Likely Time 6 2 6 8 9 3 7 4 6 5 9 4 2 8 Pessimistic Time 7 3 6 11 18 6 8 8 7 11 6 3 10